A can lay a railway track between two given stations in 8 days and B can do the same job in 24 days. With the help of C, they can do the job in 3 days. C alone can do the job in:

A
7 days
B
8 days
C
6 days
D
9 days
Result Summary
Logo

APEDIA

NTPC Graduate Tier 1
2025 • 09 Jun, 2025 • Shift-1
A can lay a railway track between two given stations in 8 days and B can do the same job in 24 days. With the help of C, they can do the job in 3 days. C alone can do the job in:
Correct Answer
6 days
Rate of Work Formulation: In time and work matrices, an individual's efficiency is mathematically evaluated as the reciprocal of their completion time. A's dail......
💡 Analysis & Explanation
Rate of Work Formulation
In time and work matrices, an individual's efficiency is mathematically evaluated as the reciprocal of their completion time. A's daily independent work rate is 1/8. B's daily independent work rate is 1/24.
Combined Efficiency Evaluation
When working as a highly synchronized team (A + B + C), they finish the entire task in exactly 3 days. Therefore, their collective daily work rate is exactly 1/3.
Variable Isolation (Finding C)
The collective equation is formed as: (1/8) + (1/24) + (1/C) = (1/3). We must align the denominators to strictly isolate C. Creating a common denominator of 24, we convert the equation: (3/24) + (1/24) + (1/C) = (8/24).
Final Mathematical Derivation
Combining the known fractions gives (4/24) + (1/C) = (8/24). By shifting terms, we deduce 1/C = (8/24) - (4/24) = 4/24. Simplifying this fraction drastically leaves 1/6. By reciprocating, C's total time is revealed.
Conclusion
Worker C, operating entirely independently, requires exactly 6 days.